一、安裝方法
1、 Installation method
1、根據所需的水平高度,垂直和垂直繪制水平線;
1. Draw horizontal lines vertically and vertically according to the required horizontal height;
2、根據起吊輕鋼龍骨的適當間距(38或50),一般間距為1-1.2米,根據輕鋼龍骨吊桿的距離分布;
2、 According to the appropriate spacing (38 or 50) of lifting light steel keel, the general spacing is 1-1.2 meters, according to the distance distribution of light steel keel suspenders;
3、安裝時必須帶上手套,如不小心留下指紋或污漬,可用洗滌液用水擦干;
3. Gloves must be worn during installation. If fingerprints or stains are left carelessly, they can be dried with washing solution and water;
4、預先安裝在龍骨吊件上,即使是同方通過龍骨安裝在輕鋼龍骨下面,方龍骨間距一般為1米,均須在裝載后調整到水平面;
4, pre installed on the keel suspension, even if the same side is installed under the light steel keel under the same side through the keel, the square keel spacing is generally 1 meters, all must be adjusted to the horizontal plane after loading.
5、鋁單板/木紋鋁單板/鋁單板吊頂系列為了扣住并掛在龍骨上,再按下反向鎖板,方端應保持0mm或20mm的距離。
5、 Aluminum veneer / wood grain aluminum veneer / aluminum veneer ceiling series in order to buckle and hang on the keel, and then press the reverse lock plate, the square end shall be kept at a distance of 0mm or 20mm.
二、鋁單板安裝主要注意事項:
2、 Main precautions for installation of aluminum veneer:
1.搬運和搬運過程中應輕放輕放。鋁單板在受到嚴重沖擊后,其邊角和布局都會受到破壞,影響施工,浪費資金。
1. Handle with care during handling. After the aluminum veneer is seriously impacted, its corners and layout will be damaged, which will affect the construction and waste funds.
2.在安裝鋁單板時,也要注意保護板材表面,不要用板材表面接觸地面,以免劃傷裝飾表面。
2. When installing the aluminum veneer, also pay attention to protect the surface of the plate. Do not touch the ground with the plate surface to avoid scratching the decorative surface.
3.鋁單板的品種、質量、顏色、圖案、線條等應符合設計要求,并具有產品合格證。
3. The variety, quality, color, pattern, line, etc. of aluminum veneer shall meet the design requirements and have the product certificate.
4.采用鋼龍骨的幕墻框架,其規格及外形應符合設計要求,并進行除銹防銹處理。
4. For the curtain wall frame with steel keel, its specification and appearance shall meet the design requirements, and the rust removal and anti rust treatment shall be carried out.
5.鋁飾面安裝時,當設計沒有特殊要求時,盡量采用抽芯鋁鉚釘,中間必須填充橡膠圈。抽芯鉚釘間距控制在100-150mm內。
5. During the installation of aluminum facing, when there is no special requirement in the design, pop rivets shall be used as far as possible, and rubber rings shall be filled in the middle. The spacing of pop rivets shall be controlled within 100-150 mm.
6.鋁單板安裝完成后,務必在3天后撕掉保護膜。如果時間太長,很難撕下,撕下后會影響外觀。
6. After the installation of the aluminum veneer, the protective film must be removed after 3 days. If the time is too long, it is difficult to tear it off, which will affect the appearance.
以上是鋁板生產廠家為大家介紹的相關內容,想要了解更多內容,歡迎訪問網站:http://www.kangyanghua.com
The above is the relevant content introduced by the aluminum plate manufacturer for you. To learn more, please visit the website: http://www.kangyanghua.com